When I walk a foothills property with a buyer, the extra bedroom downstairs is easy to see. The system that has to serve it is buried in the yard. Before we count that room, I want the county file, the permitted bedroom count and a drawing that shows where the wastewater goes.

Buying in Conifer, selling acreage near Elizabeth, or comparing homes with Littleton mailing addresses? Start with the county transfer map and contractor directory. Then use this guide to decide which inspections to order and which documents to ask for.

What does “septic tank only” mean?

If a listing says “septic,” my first question is where the water goes after it leaves the house. Two lids in the yard can belong to one tank with two compartments. They tell you very little about the rest of the system. Ask for the approved drawing, often called an as-built, and have the inspector walk you through it.

Septic tank with a leach field
Wastewater travels through the house sewer to the tank. Solids settle, grease floats, and liquid flows to a soil treatment area, also called a drainfield or leach field. Soil beneath the distribution area provides further treatment. Pumping removes accumulated solids; a pump truck does not replace the field’s job.
Sealed holding tank or vault
A watertight vault stores wastewater until a hauler removes it. There is no discharge to a leach field. Ask for the operating permit, tank capacity, alarm information and a year of hauling receipts. A vault serving a weekend cabin can have a very different operating cost once people live there full time. Jefferson County allows certain full-time residential vaults with an approved operating permit.
Engineered and higher-treatment systems
A pump may dose a field under pressure; a mound can provide additional treatment depth, and an aerobic treatment unit adds a treatment step before dispersal. A pump chamber is therefore different from a sealed holding tank. On a steep or shallow-soil foothills lot, ask the designer or county why that particular system was approved and whether monitoring, electricity or a service agreement is required.

EPA illustrated system guide · Jefferson County’s 2026 vault update

Why does the permit say three bedrooms when the house has four?

A bedroom count gives the designer a way to estimate how many people may regularly shower, cook and do laundry there. Square footage alone tells us little about that wastewater load. The county evaluates design flow, tank capacity, soil conditions and the treatment area together. A bigger tank by itself does not increase the permitted bedroom count.

Colorado baseline residential design examples under Regulation 43
BedroomsAssumed peopleDesign flow
24300 gal/day
36450 gal/day
47525 gal/day

The baseline uses 75 gallons per person per day, two people per bedroom through three bedrooms, and one additional person for each additional bedroom. Local adjustments are allowed. These examples explain the math; the figure that matters for your home is on its approved record. Colorado Regulation 43, section 43.6 and Table 6-1

My advice on a finished basement: If you’re counting on a fourth bedroom and the permit says three, ask Environmental Health about the discrepancy and any required upgrade before you price, advertise or commit to the home. A legal egress window answers a different question from wastewater capacity.

What is a septic use permit at the time of sale?

It’s the local health agency’s documentation that a system meets its conditions for continued use or transfer. Depending on the county, the document might be a use permit, transfer certificate or acceptance document. The original construction permit shows what was authorized when the system was built. The transfer paperwork addresses its status for this transaction.

  1. Pull the file. Get the installation permit, final approval, approved bedroom count, as-built, service records and any current operating permit. If the file is missing, ask the county how it handles undocumented systems.
  2. Book the right people. Check the county’s accepted inspector qualifications and pumper license. Ask whether inspection and pumping must be coordinated so the inspector can observe the system before the tank is emptied.
  3. Complete the county file. Depending on the program, this may include an application, fee, signed report, pumping receipt, sketch and evidence of repairs or a maintenance contract. Ask who submits it and who will receive the issued document.
  4. Resolve deficiencies before closing. Get written direction on repairs, reinspection or an approved transfer agreement if available. A paid invoice and a signed inspection report can still leave county approval outstanding.

A transfer inspection records observed conditions on the inspection date. It cannot tell you how many years a field has left. Check parcel jurisdiction, exemptions and document expiration with the authority before relying on a prior sale’s paperwork.

What does a septic inspector actually check?

Ask the inspector to identify the tank and field on the plan, explain which components they could access, and distinguish observed defects from areas they could not evaluate. A typical review may include liquid levels, tank condition, inlet and outlet components, pumps or alarms where installed, and signs of ponding or wastewater surfacing in the treatment area. Accessible components and county forms vary.

I want the written report to answer three questions: What did you see? What couldn’t you see? What should the buyer or seller do next? A pump receipt records a service. It does not tell me whether the disposal field was inspected. Douglas County’s component and transfer requirements

Does the transfer inspection include the sewer line from the house?

Plan on ordering a separate sewer scope unless the inspector explicitly includes it in writing. An inspector may observe flow into the tank or examine the inlet. Neither gives you a camera view of the buried pipe between the house and tank. For example, Douglas County lists the tank, applicable pumps and controls, and soil treatment area in its transfer process. A complete camera recording of the building sewer is a different deliverable.

For buyers: During your contract inspection window, ask a qualified scope provider to video the line from an accessible cleanout toward the tank. Request the video, the distance reached, any sections they could not see, and locations of roots, offsets or breaks. If access stops the camera early, find out what remains unknown before your deadline.

For sellers: Locate the cleanout and lids, make them accessible and gather past line repairs or scope videos. Even after a county use permit is issued, a buyer may reasonably want this separate inspection. Give both providers the as-built so they know which pipe and tank serve the house.

Which Front Range counties require septic transfer paperwork?

Of the 16 counties mapped here, 13 have a process for qualifying transfers. El Paso offers optional county review. Denver and Weld publish no county sale requirement. This regional guide includes nearby foothills counties where my clients shop. Use the parcel’s county and governing health agency, even when the mailing city suggests somewhere else.

Boulder · Required for covered transfersBroomfield · Required for covered transfersDenver · No county sale requirementDouglas · Required for covered transfersGilpin · Required for covered transfersJefferson · Required for covered transfersWeld · No county sale requirementAdams · Required for covered transfersLarimer · Required for covered transfersTeller · Required for covered transfersClear Creek · Required for covered transfersEl Paso · Optional county reviewPueblo · Required for covered transfersArapahoe · Required for covered transfersElbert · Required for covered transfersPark · Required for covered transfersLarimerWeldBoulderAdamsArapahoeJeffersonDouglasElbertParkTellerEl PasoPueblo
County sale rules · November 2026
Required for covered transfersOptional county reviewNo county sale requirement
Select an outline or a county name. Boundaries are for regional orientation. County geometry source

Where can I find an accepted pumper or inspector?

Colorado counties use different credentials. A cleaner’s license covers pumping; the person signing the inspection may need a separate credential, such as National Association of Wastewater Technicians (NAWT) certification. The entries below distinguish official roster examples, credential lookups and provider-reported leads. Before booking, ask the county to confirm both roles for your address and system type.

Required for covered transfers

Adams

Obtain a use permit for a covered transfer. The county accepts NAWT- or NSF-certified inspectors and says pumping is needed in most cases.

Pumping and inspection. A-1 Septic Service, Spenser Rickman (303-659-0610), is listed for cleaning and use-permit inspection. Colorado Pumping LLC (303-278-1884) is listed for cleaning; Steve Dickinson, 2D Enterprises (303-638-2772), for inspection.

Required for covered transfers

Arapahoe

Request the existing permit and site sketch, then follow Public Health’s transfer-of-title use permit process.

Pumping and inspection. County-listed pumpers include A-1 Septic Service (303-659-0610) and Honeybee Pumping Service (303-648-3558). NAWT lists inspectors Spenser Rickman of A-1 and Austin Bitz of AB Septic (720-883-3390). Confirm the individual credential when scheduling.

Required for covered transfers

Boulder

Request a Property Transfer Certificate. Check both system function and permitted bedroom capacity. A written repair agreement may be an option with county approval.

Pumping and inspection. County lists Sullivan Septic (303-772-4019) and Gapter Septic Pumping & Services (720-896-0618) under both cleaners and transfer inspectors.

Required for covered transfers

Broomfield

Check with Water Utilities (303-438-6319) about a public sewer main within 100 feet before applying for the transfer permit.

Pumping and inspection. Listed cleaners include JT Pumping (303-910-7323) and A-1 Septic Service (303-659-0610). For inspection, Broomfield accepts NAWT certification or an approved equivalent and does not license transfer inspectors. Confirm eligibility with Environmental Health at 720-887-2220.

Required for covered transfers

Clear Creek

Check whether any component has been in use more than five years or the permit limits occupancy or bedroom use. The covered sale file includes an inspection report, pump receipt, application and listing or sale publication.

Pumping and inspection. Evergreen Septic Pumping Co. (303-674-7144) appears for pumping and inspection in the county’s historical roster and in a 2026 county record. Confirm current eligibility for both roles before booking.

No county sale requirement

Denver

Denver’s OWTS rules say a transfer-of-title inspection is not required. Ask the city which rules apply if you plan repairs or a change of use.

Pumping and inspection. Denver accepts cleaners licensed by another Colorado county or local public health agency. Nearby Jefferson lists Foothills Septic Pumping (303-670-3160) and Evergreen Septic Pumping Co. (303-674-7144). Confirm coverage. Denver has no required transfer-inspector roster for this purpose.

Required for covered transfers

Douglas

The use permit process reviews the tank, soil treatment area and applicable pumps and controls. Ask the county about a buyer repair agreement if the system fails inspection.

Pumping and inspection. A1 Pumping and Septic Services (719-330-1461) and Absolute Diversified Services LLC (303-688-9201) appear in the county’s combined cleaner/inspector directory. Confirm the role of the person dispatched and current licensing.

Optional county review

El Paso

The county makes its property-sale inspection review optional. A buyer can still order an inspection and request county review under the published process.

Pumping and inspection. Cleaners include Alpine Septic (719-464-4845) and TCS Septic Pumping (719-492-6818). Listed inspectors include Timothy Edwards, Absolute Septic (719-689-7867), and Dennis Williams, ACME Sewer & Drain (719-264-9493).

Required for covered transfers

Elbert

For a covered transfer, obtain the use permit using a county-licensed inspector’s report and the county application.

Pumping and inspection. Elizabeth Septic (303-919-0923) and American Pumping (303-841-7150) are listed for pumping and inspections. JT Pumping (303-910-7323) is listed for pumping and Cardinal Consulting (740-248-9895) for inspections.

Required for covered transfers

Gilpin

For covered unincorporated properties, the county directs sellers to begin before going under contract. There are exemptions for certain recently permitted and installed systems. Sealed vaults are covered; higher-level treatment has additional operating and maintenance paperwork.

Pumping and inspection. Evergreen Septic Pumping (303-674-7144) reports serving Gilpin for pumping and inspections. Confirm the current pumper license and individual inspector with Community Development at 720-617-7779; the provider’s statement is not county verification.

Required for covered transfers

Jefferson

The county says a sale triggers its use permit requirement for systems installed more than five years before the sale date. Request the county’s final permit along with the inspection and pumping records.

Pumping and inspection. Foothills Septic Pumping (303-670-3160) and Evergreen Septic Pumping Co. (303-674-7144) appear on both the county cleaner and inspector lists.

Required for covered transfers

Larimer

Covered sales need an Acceptance Document before closing. The county describes a 12-month window from inspection and lists exceptions.

Pumping and inspection. Johnston Sanitation Service (970-667-5405) provides pumping and inspections. Verify current credentials in the separate inspector and cleaner lists linked by the county.

Required for covered transfers

Park

The transfer checklist calls for a NAWT-certified inspector, a sketch, a pumping receipt, an application and a fee. Confirm any exemption with Environmental Health.

Pumping and inspection. County-listed pumpers include Absolute Septic (719-689-7867) and Shirley Septic (303-838-6033). Evergreen Septic Pumping (303-674-7144) reports providing inspections in Park. Verify the individual’s current NAWT credential and county acceptance at 719-836-4267.

Required for covered transfers

Pueblo

Covered sales need pumping, inspection and acceptance before closing. County acceptance lasts 12 months or until transfer, whichever comes first.

Pumping and inspection. Budget 8 Septic Service (719-565-8470) and Cut Rate Sewer & Drain (719-564-2221) appear on the county roster for both services.

Required for covered transfers

Teller

The county’s transfer program took effect July 24, 2026. Check the exemption list and whether an acceptance or continued-use application fits the transaction.

Pumping and inspection. The county transfer-inspector list names Timothy Edwards of Absolute Septic LLC (719-689-7867) and Chris Diethelm of Alpine Septic (719-464-4845). Arrowhead Septic advertises pumping in Teller County. Confirm the cleaner’s current county license separately. Check the county’s license search and transfer-inspector list or call 719-687-6416 before hiring.

No county sale requirement

Weld

The county explicitly has no transfer inspection or use permit requirement for a sale. It encourages a private inspection and cleaning before ownership changes.

Pumping and inspection. Johnston Sanitation Service (970-667-5405) is a pumping lead; check the county’s current cleaner record. For a voluntary inspection, separately confirm inspector training and scope. Weld’s directory lists cleaners, engineers and installers rather than a transfer-inspector class.

What I’d keep in the closing file

Save the permit and as-built, dated inspection, pumping receipt, scope video, any repair invoices and the county’s final decision. Give the next owner the inspection access points and maintenance schedule. If the seller describes a four-bedroom home and the permit describes three, resolve that question in writing while you still have choices.